Stakeholder Groups
- eIAM internal stakeholders We work according to the SAFe methodology, this promotes alignment, collaboration and execution across the different eIAM teams. eIAM focal points
- eIAM-external stakeholders in the course of the project and in operation For customer project, under the responsibility of the PM customer/partner, the following stakeholder groups/stakeholders must be addressed and held accountable at certain stages of the eIAM integration:
- Initial contact/main point of contact
- PM customer/partner
- Ev. PM BIT
- Ev. other central contact persons
- In a first coordination phase (TechInfos questionnaire), i.e. before commissioning eIAM, the PM customer/partner must take the following stakeholder groups into responsibility
- Business
- Development/Architecture
- With regard to the integration phase, the commercial stakeholder groups may become relevant
- Integration Manager (IM) in office
- Ev. OFM
- Ev. Account Manager (AM) in BIT
- For the concrete preparation of the integration phase, the PM Customer/Partner has to take the following stakeholder groups into responsibility
- Contact person Infrastructure Provision Server
- Main contact person for testing/test management
- Overall coordinator of all user administrators of an office (GKA)
- Main contact person for user administrators of an application/site (BVA) of this specialised application
- During the integration phase on REF, ABN and PROD, the PM customer/partner has to ensure the coordination of eIAM with the following stakeholder groups
- Contact person development integration eIAM
- Contact person Infrastructure Provisioning Server
- Contact person Testing eIAM
- In the final phase (supplementary information before handover of operations), the PM customer/partner must make the following stakeholder groups responsible
- Contact person specialist - specialist application manager
- Who is authorised to issue change requests for roles to eIAM?
- Who is authorised to issue change orders to eIAM for adjustments regarding QoA ()?
- Specialist 1st-Level Support Specialist Application
- Development 3rd-Level Support
- Contact person for regression tests in the context of eIAM service releases
- Application operation as contact person for lifecycle according to golive
- Stakeholder groups end-user In the context of implementation and operation, the following service users/end users are relevant:
- Enduser eIAM
- GKA (Enterprise context)
- BVA (enterprise context)
- Delegated Manager (Enterprise or eGov context)
- Enduser Enterprise context
- End-user eGov context
Potential stakeholder groups / contact persons (as of today, it is not yet clear whether these stakeholder groups will be included in the above group)
- Governance at LB
- CISO for QoA
- PM BIT